01Prequalification submittal
Company profile and role, organisation chart with key personnel, ISO certificates, accreditations, local registration, completed projects, plant and equipment list.
02Site survey report
Objective, location and coordinates, tools used, methodology, drawings, identification and summary.
03System design and simulation report
Produced with PV*SOL or PVsyst using recent local climate data, and subject to technical review before approval.
04Material submittal
Supplier profile, detailed BOQ, component data sheets, warranty terms, country of origin and previous approvals.
05Shop drawings
IFC, infrastructure, solar system and electrical room drawings — verified by the QA/QC engineer for contents, clarity, annotations, line weights, numbering and revision status, then stamped and signed before submission.
06Method statements and ITP
Scope, definitions, material, tools, manpower, safety requirements, method of installation, connections, system architectures and Inspection Test Plans. Work may not start before a method statement is approved.
07CRFI, checklists, NCR and CAR
Inspections are carried out within one business day of the request, by quality inspectors only. Non-compliance raises an NCR and a CAR within one business day, and all of them are archived and circulated so they are not repeated.
08As-built drawings
Red line sketches during construction, consolidated into as-built drawings for final review and approval on completion.
09O and M manual
Delivered to the end user on completion, in compliance with the client's O&M manual specification.